MINING REMEDIATION AUTHORITY ADDRESS PLATEThe Mining Remediation Authority’s new Dalkeith mine water treatment scheme has reached a significant phase in its development, with excavation works now under way and key construction milestones successfully completed.

The Mining Remediation Authority’s new Dalkeith mine water treatment scheme has reached a significant phase in its development, with excavation works now under way and key construction milestones successfully completed.

MRA_Dalkeith_mine_water_treatment_scheme_construction_site_August_2025.jpg

Photo:Site overview of Dalkeith mine water treatment scheme in August 2025

Following the site clearance, surveys, ground stabilisation and setup of construction facilities, the project – being built by the Mining Remediation Authority (MRA) as part of its work in coalfield areas of Scotland – is moving into its next stage.

The scheme, funded by the Department for Energy Security and Net Zero, is being built to clean water coming from the former Bilston Glen colliery, which has been discharging through a historical mine passageway called Old Fordell adit, also known locally as Junkies Adit.

This has been turning stretches of the River South Esk orange, as high levels of dissolved iron, picked up from the extensive network of old mine workings, becomes solid when it mixes with air and settles out of the water.

During periods of heavy rain, the adit can flush up to 300l/s of mine water into the river.

The solution for the mine water discharge at Dalkeith is to construct an active High Density Sludge (HDS) mine water treatment scheme – the MRA’s contractor J.N Bentley are carrying out the work.

MRA_DALKIETH_HIGH_DENSITY_SLUDGE_TREATMENT_SOLUTION.jpg

The local community is now being invited to preview the final design through an interactive virtual tour and have a say on the landscaping of the finished scheme, as well as find out more about what works are planned later this year.

Josh Turner, of the Mining Remediation Authority’s community response and stakeholder engagement team, said:

We’re really excited to welcome the people of Dalkeith to our drop-in event at the town’s library on Thursday 25 September. It’s a great chance to see how the mine water treatment scheme is progressing, explore the site in 3D, and share your ideas on landscaping and screening.”

Over the next few months:

site levelling will continue after the retaining walls are in place

piling works will be followed by the placing of concrete foundations

construction will start on the walls of the treatment building

MINING REMEDIATION AUTHORITY ADDRESS PLATE

Generate More Business

Increase your sales by targeting Waterbriefing's named readership of over 8000 water industry professionals:

Showcase your Company

Include news about your latest product or technology and receive home page coverage. Click here.

Join our Directory

Make it easy for prospective customers to find out about your services. Click here.

Promote your Story

Make your company news the first story Waterbriefing users see, via our scrolling news feature. Click here.

Place an Advert

Promote your expertise through an online banner ad, with packages to suit every budget. Click here.